atlantic-avenue-constructionThe repaving project of Atlantic Avenue (from Bixby Road to San Antonio Drive) is nearly complete!

Last week the rubberized asphalt was put down at night and the contractor will be working on the final steps of the project. 

Already, the noise has been significantly reduced on Atlantic with the rubberized asphalt. However there are still a few items to complete before the construction on Atlantic will be done:

  • This week the contractor begins installing decorative pavers in the cross walks at Bixby, Roosevelt, and Carson. Atlantic Avenue  will be restriped.
  • Next week, the restriping of Atlantic Avenue will take place with final walk-throughs with the city traffic engineer. 
  • The contractor will go back through to make sure everything has been repaired and cleaned up before leaving for good.

Status updates will be regularly posted at www.bixbyknollsinfo.com/atlantic_construction.html. Keep and eye out in the near future for details on the “Grand Re-Opening Celebration” of Atlantic Avenue.